Spacer
Spacer Spacer Spacer
Spacer
National Aeronautics and Space Administration NASA
NASA Spacer
+ Goddard Space Flight Center
+ Sciences & Exploration Directorate
+ Astrophysics Science Division
spacer
spacerGo
spacer
Advanced Search
Spacer
FAST FACTS spacer FAQ spacer GLOSSARY spacer CONTACT US
Spacer
Spacer
HOME
spacer

STATUS
+ Current Status
+ Recent
   Accomplishments
+ What's Next?
spacer
NEWS
spacer
ABOUT THE WEBB
spacer
SCIENCE
spacer
INSTRUMENTS
spacer
FEATURES
spacer
IMAGES & VIDEOS
spacer
MEET THE TEAM
spacer
FOR SCIENTISTS
spacer
FOR EDUCATORS
spacer
FOR PRESS
spacer


RSS news feed RSS
Twitter Twitter
Facebook Facebook
YouTube channel YouTube
Flickr Flickr


Recent Accomplishments

Updated May 14, 2012

The following list contains a record of program and project accomplishments for the James Webb Space Telescope.  The left column gives the original due date, the middle column gives the item accomplished, and the right column indicates the schedule performance with green text denoting items accomplished earlier than planned, black text for items completed on schedule, and red text for items finishing later than planned. The list will be updated approximately every month.  

The image below points out various major hardware components of the facility referred to in the list to orient the reader. (Click to enlarge image.)

Labeled Spacecraft

Due Date

Item Accomplished

Completion Date

May, 2012

Finish testing the COCOA

Measure Sunshield template layer 5 shape to confirm its accuracy

March 9, 2012

April 23, 2012

April, 2012

Complete all composite parts for mechanism that lifts telescope away from spacecraft after launch (Deployable Tower Assembly)

February 28, 2012, completed two months early

March, 2012

Deliver ISIM computer #2 to ISIM integration and testing. (Single synchronous dynamic random access memory chip failure during computer thermal vacuum testing. Chip is being replaced and computer retested. )

Complete analysis of JSC Thermal Vacuum Chamber telescope testing equipment plans

System Engineering Team to complete assessment of instrument thermal margins

Delivery now May

 

 

 

March 19, 2012

 

March 1, 2012


February, 2012

Install Helium shroud walls at JSC Thermal Vacuum Chamber

Complete assembly and initial testing of main mirrors at Marshall Space Flight Center

February 2, 2012, (all panels, walls, floor, ceiling, door)

December 19, 2011, Completed two months early

January, 2012

Conduct Critical Design Review for Spacecraft-to-Optical Telescope Element vibration isolation system

Finish building Center of Curvature Optical Assembly ("COCOA") for testing primary mirror in JSC TVC

Review preliminary requirements for ground structure for spacecraft equipment panels

Complete Aft Optic System integration and alignment

Update Program Plan and Program Commitment Agreement to reflect replan

December 15, 2011, Completed one month early


January 19, 2012



December 1, 2011, Completed one month early


December 2, 2011, Completed one month early

January 28, 2012

December, 2011

Install Helium shroud floor at Johnson Space Center thermal vacuum chamber ("JSC TVC")

Determine root cause of NIRSpec optical bench flaw

October 27, 2011 Completed two months early

December 15, 2011

November, 2011

Complete electronics simulator model for Integrated Science Instrument Module ("ISIM")

Deliver tools for software development environment and verification

November 15, 2011



October, 27, 2011 Completed one month early

October, 2011

Begin construction of 140,000-lb robotic facility to build segmented main mirror at GSFC

October 4, 2011

September, 2011

Deliver Flight ISIM Electronics Compartment to ISIM Integration & Test

Deliver flight ISIM Command & Data Handling unit #1 to ISIM Integration & Test

Deferred/design change


September 27, 2011

August, 2011

Spacecraft Flight Software Build 1 Technical Readiness Review

June 30, 2011, Completed two months early

July, 2011

Deliver ISIM Region 1 Wiring Harnesses

Deliver ISIM Structure to ISIM Integration & Test

July 22, 2011

July 28, 2011

June, 2011

Complete Common Command & Telemetry System Build 2.3

Start ISIM level Integration & Test

April 13, 2011, Completed two months early

June 24, 2011

May, 2011

Start flight Fine Guidance Sensor environmental testing (instrument level)

Complete Spacecraft Secondary Mirror Segment Cone Structure internal Design Review

May 5, 2011


April 20, 2011 Completed one month early

April, 2011

Pathfinder Primary Mirror Segment Assemblies complete

Deliver ISIM Command & Data Handling test unit to ISIM Integration & Test

Complete 2018 Launch Readiness Date project lead Joint cost & schedule Confidence Limit (JCL)

April 25, 2011


April 22, 2011


April 28, 2011

March, 2011

Complete flight ISIM Remote Services Unit Thermal Vacuum testing

Deliver Fine Guidance Sensor (FGS) test unit electronics to ISIM Integration & Test

Complete 2018 Launch Readiness Date budget details

February 19, 2011, Completed one month early

February 24, 2011, Completed one month early

April 7, Completed one week late

February, 2011

Deliver Near-Infrared Spectrograph flight spare detector to GSFC

Pathfinder Primary Mirror Backplane Support Structure delivered to Northrop-Grumman Aerospace Sys.

Establish No-Earlier-Than Launch Readiness Date as part of replan

Establish Work Breakdown Structure for new GSFC responsibilities

January 29, 2011, Completed one month early

March 25, 2011, Completed one month late (weather conditions affected shipping)

February 25, 2011


February 28, 2011

January, 2011

Ship Mid-Infrared Instrument (MIRI) Focal Plane Electronics to ESA (Rutherford Appleton Lab.)

Ball's Flight Actuator Drive Unit Software Test Review

January 20, 2011


January 24, 2011

 

Spacer
NASA Home 
Page ESA Home 
Page CSA Home 
Page

Webmaster: Maggie Masetti

Responsible NASA Official: John Durning

+Privacy Policy and Important Notices

Spacer
Spacer Spacer Spacer